Project Spotlight

Location
West Swanson Dock, Melbourne
Project Value
Multi-million dollar
QEST Infrastructure successfully delivered a High Voltage riser installation within the highly constrained, fully operational environment of West Swanson Dock. The project demanded high-risk construction activities, extensive site investigations and specialist trenchless techniques, all delivered with zero impact on dock operations, shipping movements or existing port assets.
The Challenge
Installing HV conduits beneath the pavement of an existing, fully operational dock, one of Melbourne’s busiest, left no margin for error. Laser boring was selected as the trenchless technology to carry the conduits through, with the drilling performed from below sea level. Sheet piling, jet grouting and dewatering were implemented to achieve this. The project had to be delivered under significant technical and operational constraints:
- Zero damage permitted to dock infrastructure
- No disruption to shipping movements
- Tidal influences dictating the available construction windows
- Highly challenging ground conditions, including the notorious Coode Island Silt
- Active groundwater management throughout
- Strict environmental controls, with no contamination permitted
- Precision drilling requirements in close proximity to critical port assets
Our Approach
QEST’s integrated, multi-division capability meant the entire delivery chain stayed under one roof, from the first survey to the final plug installation:
- Detailed upfront planning and staging, in close liaison with DP World and the port authority
- Comprehensive environmental and geotechnical investigations before a single tool touched the ground
- Full dock service locating and surveying to verify every existing asset
- Selection of trenchless, low-impact construction methods, including precision horizontal laser boring through groundwater to control line and level
- Sheet piling, jet grouting, structural slab construction and conduit installation for the HV services
- Robust safety, environmental and quality management systems, coordinated across all stakeholders and third-party engineers
Specialist technique: precision horizontal laser boring allowed the team to hold exact line and level with an accuracy of 1mm for over 50 metres of drilling while working from below sea level, through waterlogged and unstable ground where conventional excavation would have put dock assets and the environment at risk.
The Outcome
✓ High Voltage riser installed safely and successfully
✓ Zero impact on dock operations or shipping movements
✓ No damage to any existing port asset
✓ Full environmental compliance with zero contamination
✓ Challenging ground and groundwater conditions managed effectively
✓ Seamless coordination with client, port authority and third-party engineers